Enterprise Ireland
carried out baseline noise measurements at nine locations along the
proposed route and along the N18. Computer models were used to predict
noise levels at all sensitive locations (23 in total) along the proposed
route for the 'do-nothing' and the 'do-something' scenarios both for 2008
and 2028. For the purposes of the LSRR Phase II project, where noise levels
due to the road scheme are greater than or equal to 68dBLA10 (18 hour) in
2028, mitigation measures will be provided.
Of the 23 prediction locations along the scheme, 14 will be above the
68dBLA10 (18 hour) criterion in 2028. Mitigation measures such as noise
barriers or bunds will be applied near the road in the vicinity of all
properties where noise levels are predicted to increase to 68 dBLA10-18hr
or above due to noise generated by traffic on the new scheme. With these
measures in place, no existing property along the proposed route will
experience increases in noise levels to 68 dBLA10-18hr or above due to
traffic using the new scheme.
At one of the 14 locations - the R526 (St. Nessan's Road) - noise levels
already exceed the 68 dBLA10-18hr without the proposed road in place. The
R526 will be realigned over the mainline as part of the scheme with the
result that the road will be moved further away from housing on the
existing road. This together with the predicted reduction in traffic flow
on the R526 due to the overall scheme will reduce traffic noise at this
location.
The ground vibration from the operation of the new road will be expected to
be several orders of magnitude less than that which may cause disturbance
or structural damage. The vibration will be less than that caused by
traffic on the surfaces of the existing roads.
A variety of items of machinery will be used during the construction phase
of the development and some have the potential to create adverse noise
conditions. The contractor will be obliged to manage and control noise on
site during the construction period through the implementation of
mitigation measures including the restriction of working hours and the
adherence to the guidance set out in British Standard BS 5228 1997 "Noise
Control on Construction and Demolition Sites". It should be noted that
although construction of the proposed road and tunnel will take
approximately four years to complete, the impact and the disruption at
individual locations will only be for the duration construction works are
taking place in proximity to that location.