

The Limerick Tunnel Project consists of the construction of approximately
10km of dual carriageway with grade separated intersections and includes
the Limerick Tunnel under the River Shannon Southwest of the City.
| Key Facts | ||
![]() |
Start Date | August 2006 |
| Completion Date | September 2010 | |
| Overall Length | 10Km | |
| Major Interchanges | 4 | |
| Number of Structures | 17 | |
| Length of Tunnel | 675m | |
| Toll Collection Locations | 2 | |
| Volume of Excavation | 300,000 m3 | |
| Volume of Fill | 3,100,000 m3 | |
From the start of the scheme at the N7/N20 Rossbrien Interchange to
Bunlicky Lake, a distance of 4.5km, the existing ground levels range from
approximately +12.4m to 1.5m above sea level. Over the vast majority of the
length the general level is below +2.00m above sea level.
There is only one short 300m section where the road alignment is in cut.
The fact that the majority of the existing ground levels are so low (approx
+2.0m above sea level) means that most of the mainline has to be built up
by over 3m (to a level +5.2m above sea level) to ensure protection from
flooding. This will involve the importation of approximately 3.2 million m3
of suitable fill material.
The geological conditions underlying the route corridor present a number
of geotechnical issues to be addressed in the design of the scheme.
The major issues are summarised as:
The difficult ground conditions present many difficult engineering problems
including ground stabilization. In addition to the mainline earthworks,
some 500,000m3 will be excavated from the area of the Tunnel
casting basin to the north of the River Shannon.
The dredging activity in the River Shannon prior to placing of the immersed
tube units will generate an additional 400,000m3 of material
which will be suction dredged and placed in lagoons.